Most small scale generation will require a dedicated transformer. The size of transformer needed is dependent on the capacity (kW) and type of the generator to be installed. Typically:
- A pole mounted single phase transformer can be used for generator capacities up to 17kW
- A pole mounted three phase transformer can be used for generator capacities up to 150kW
- A ground mounted transformer/substation is necessary for generator capacities over 150kW